KSEB per kVA Rate Calculator

per kVA/kW Rate Calculator

Standardized Electricity Connection Charge Estimator (KSERC Order OP No. 34/2026)

Connection Details

kW
Single Phase: ≤ 5 kW | Three Phase: > 5 kW up to 100 kW/kVA
per kVA rates apply within 200m (+ 35m WP cable allowance).
Distance Exceeds 200m:per kVA/kW rates do not apply. Expenditure will be recovered based on actual Cost Data estimate under Regulation 36/37.

Estimation Breakdown

Single Phase (240V)

Applied Load & Supply Voltage
3.00 kW (Low Tension)
Description of Works
LT single phase service connection above 2 kW up to and including 5kW
Applicable Rate Slab: Fixed Slab (₹ 5,000 / connection)
Estimated Cost of Service Connection: ₹ 5,000
Security Deposit (₹ 300/kW): ₹ 900
Application Fee: ₹ 50
Total Estimated Amount Payable
₹ 5,950
Rates approved as per KSERC Order in OP No. 34/2026 under Section 46 of Electricity Act 2003 & Supply Code, 2014.

Supply Code Regulations & Guidelines

Key rules governing electricity supply infrastructure and rate application in Kerala

Supply Voltage Limits
  • Single Phase (240V): Connected load up to 5 kW.
  • Three Phase (415V): Load > 5 kW up to 100 kW/kVA.
  • HT Supply (11 kV): Contract Demand > 100 kVA up to 3,000 kVA.
200m Electrified Boundary

Standard per kVA/kW rates apply strictly within 200 meters of existing distribution mains (+35m weatherproof cable allowance). For other applicants the Estimate cost based on the rates in the cost data of materials and work as approved by the Commission shall be applicable.

Enhancement Exemptions

Under Regulation 32(2)(iii), no additional connection charges apply if additional load is < 10% of approved load OR < 20 kVA/kW (whichever is lower), provided no service line/voltage modification is needed.